Home improvement contract and change order checklist

Use this checklist to review your paperwork on covered Pennsylvania home improvement jobs, from the signed agreement to the final invoice.

01 · Before signing

Put the whole agreement in writing.

First check whether Pennsylvania’s Home Improvement Consumer Protection Act (HICPA) covers the work and whether your registration is current if required. The project type and statutory exceptions matter.

  • Identify the parties and the job. Check the performing contractor’s registration number and contact details, the transaction date, and the approximate start and completion dates. Use the correct company name and record who is signing.
  • Define the work and the price. Write down the scope, materials, specifications, and exclusions. Check the price or required time-and-materials terms and the applicable deposit rules. Separately confirm who is responsible for permits and inspections.
  • Check the required disclosures. Review the applicable subcontractor information, insurance disclosures, consumer protection phone number, and cancellation notice under Section 7. Have any arbitration or dispute provisions reviewed before relying on them.
  • Get signatures and provide the complete copy. Give the owner the completed contract and required notices at signing. Keep the same signed version in your job file.

Pennsylvania Attorney General guidance for contractors · HICPA, Sections 7 and 9

02 · When the scope changes

Document the change before proceeding.

For covered work, HICPA requires written change orders signed by the owner and contractor for changes to the work, materials, or specifications. Document the date and price changes and check the specific rules if the job uses time-and-materials pricing.

  1. Reference the original contract and describe what changed and why.
  2. Itemize additions and credits. Show the revised price and any effect on the payment schedule or completion date.
  3. Record the date and get both signatures before proceeding with the changed work. Give both sides a copy and keep it with the original agreement.

Illustrative example

Demolition exposes damaged subflooring.

Photograph the condition and record where the damage is. Describe the extra work and the materials in the change order, itemize the additional cost, explain any schedule change, and get signed approval before starting that work.

03 · At closeout

Keep one complete job file.

Save the signed contract and notices, every approved change order, invoices and receipts, relevant messages, dated photos, and permit or inspection records. Reconcile the original price, approved changes, and payments before sending the final invoice. Keep any punch list and completion notes with that file.

This checklist highlights common issues. Check the statute and your project facts before relying on a form or clause.